Question: Find the project expected completion time. (6 points) * 25 30 29 23 The ES & EF times of activity E are: (4 points) *
Find the project expected completion time. (6 points) *
25
30
29
23
The ES & EF times of activity E are: (4 points) *
6 & 12
6 & 10
9 & 19
6 & 15
The LS & LF times of activity C are (4 points) *
5 & 9
None of the above
2 & 6
9 & 13
The slack of activity E is: (4 points) *
7
5
None of the above
8
Activity C can be delayed by: (4 points) *
3
None of the above
2
0
Activity B can be delayed by: (4 points) *
2
None of the above
4
1
The CP is: (4 points) *
A, C, E, F
NONE of the above
A, B, D, F
A, C, D, F
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
