Question: ( 2 0 points ) A certain part i s routed through six machines i n a batch production plant. The setup and operation times

(20 points) A certain part is routed through six machines in a batch production plant. The
setup and operation times for each machine are given in the following table.
The batch size is100 and the average nonoperation time per machine is12hr.
(a) Determine the manufacturing lead time
(b) Determine the production rate for operation 3.
(30 points) The average part produced in a certain batch manufacturing plant must be
processed through an average of six machines. There are 20 new batches of parts launched
each week. Other pertinent data are as follows:
Average operation time =6min
Average setup time =5 hours
Average batch size =25 parts
Average nonoperation time per batch =10 hours
There are 18 machines in the plant. The plant operates an average of70 production hours per
week. Scrap rate is negligible.
(a) Determine the manufacturing lead time for an average part
(b) Determine the plant capacity.
(c) Determine the plant utilization
(50 points)An average of20 new orders are started through a certain factory each month.
On average, an order consists of50 parts tobe processed through 10 machines in the factory.
The operation time per machine for each part =15min. The nonoperation time per order at
each machine averages 8 hours, and the required setup time per order =4 hours. There are 25
machines in the factory, 80%20% are in
repair or maintenance
 (20 points) A certain part is routed through six machines in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!