Question: 2 2 . A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion

22. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration is referred to as ______.
A. Critical path
B. Critical chain
C. Crashing
D. Fast tracking