Question: 2. (20 points) Given the information in the following table: Activity Predecessor Duration a None 4 b a 6 a 4 d 2 e b

2. (20 points) Given the information in the2. (20 points) Given the information in the

2. (20 points) Given the information in the following table: Activity Predecessor Duration a None 4 b a 6 a 4 d 2 e b 4 f bed 5 3 3 h f, g 4 i e, h 2 1) Construct the CPM network Diagram. 2) Find each activity's EST, EFT, LST, and LFT. 3) Identify all paths. Which path is the critical path? 4) Calculate the slack for each activity. 5) How long will it take to complete the project? Please make sure 100% before sending the answer. Thank you