Question: 2 . 5 A certain part is routed through six machines in a batch production plant. The setup and operation times for each machine are

2.5 A certain part is routed through six machines in a batch production plant. The setup and
operation times for each machine are given in the table below. The batch size is 100 and the
average nonoperation time per machine is 12 hours. Determine: (a) manufacturing lead time and
(b) production rate for operation 3.