Question: 2 8 . Scott has just been given a project that has a specific completion date. After a discussion with top management, he finds that

28. Scott has just been given a project that has a specific completion date. After a discussion with top management, he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as
A.
Constrained.
B.
Reduced.
C.
Accepted.
D.
Limited.
E.
Optional.