Question: Scott has just been given a project that has a specific target date. After discussion with top management, he finds that while the date is

Scott has just been given a project that has a specific target date. After discussion with top management, he finds that while the date is important, the cost is more important and a slip in delivery would be acceptable if required to meet the cost and scope targets. The target date is best classified as
Scott is managing a project which is starting to fall behind. From earlier discussions, he knows that management wants all the deliverables exactly as was identified in the project scope. Top management has expressed some flexibility to go past the deadline as long as the cost can be controlled and not exceed too much beyond the approved budget.
How should the target date be classified for this project's priority matrix?
Group of answer choices
Accept
Constrain
Enhance
Limit

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!