Question: 2. A company is evaluating three projects (Project A, Projects B, Project C). The managers expect at least 20% of Rate of Return. Which project

2. A company is evaluating three projects (Project A, Projects B, Project C). The managers expect at least 20% of Rate of Return. Which project has the highest priority based on the return on investment? Which of the projects are acceptable? If there is more than on project to be chosen, what should be the order of priority? Project A Project B Project C Investment Year Revenue Investment Year Revenue Investment Year Revenue $500,000 0 0 $250,000 0 0 $75,000 0 0 1 50,000 1 75,000 1 15,000 2 250,000 2 75,000 2 25,000 3 350,000 3 75,000 3 50,000 4 50,000 4 50,000 5 150,000