Question: #2. A). Given the following information for a project, draw the AON (Activity-On-Node) project network. a). Draw the AON (Activity-On-Node) project network. b).What are the
#2.
A). Given the following information for a project, draw the AON (Activity-On-Node) project network.
a). Draw the AON (Activity-On-Node) project network.
b).What are the estimated slack times (in weeks) for activities A-H?
c). What is the critical path.
| Activity | Immediate Processor | Activity Time (days) |
| A | - | 6 |
| B | - | 8 |
| C | A, B | 5 |
| D | B | 4 |
| E | C | 7 |
| F | C, D | 3 |
| G | D | 6 |
| H | E, F, G | 5 |