Question: A). Given the following information for a project, draw the AON (Activity-On-Node) project network. 1). Draw the AON (Activity-On-Node) project network. 2).What are the estimated

A). Given the following information for a project, draw the AON (Activity-On-Node) project network.

1). Draw the AON (Activity-On-Node) project network.

2).What are the estimated slack times (in weeks) for activities A-H?

3). What is the critical path.

Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5