Question: James has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 1 is

James has realized that two activities in his
James has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 1 is critical and has a duration of 10 days. Activity 2 has 3 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first? Activity 2. because it has higher slack Activity 1. because it is critical y Activity 2. because it has smaller doratfon Activity 1, because its ID is lower