Question: 2. Answer Questions 2a - 2c using the figure shown below: (25%) F 2a. The critical path is weeks. and its length is 3 6

2. Answer Questions 2a - 2c using the figure

2. Answer Questions 2a - 2c using the figure shown below: (25%) F 2a. The critical path is weeks. and its length is 3 6 C 6 14 3 ES H 4 5 2b. The total slack time in Activity "F" is weeks 6 7 4 B 2 5 7 G A 7 1 2c. If the crash cost/week for all activities is the same and we can crash all activities by 2 weeks except Activity H by a week and customer wants us to shorten the project length by 3 weeks we should crash Activity by week(s) first and then crash Activity by week(s). D