Question: 4. Answer Questions 4a 4c using the figure shown below: (14 points) 4a. The critical path is weeks. and its length is 2 7 4b.

4. Answer Questions 4a 4c using the figure shown

4. Answer Questions 4a 4c using the figure shown below: (14 points) 4a. The critical path is weeks. and its length is 2 7 4b. The total slack time in Activity "D" is weeks 4. A 5 3 E 5 H 1 6 B 3 5 7 2 4c. If the crash cost/week for all activities is the same and we can crash all activities by 2 weeks except Activity I by a week and customer wants us to shorten the project length by 3 weeks, we should crash Activity by week(s) first and then crash Activity by week(s). 5 6 I 4 4