Question: 2. Answer Questions 2a 2c using the figure shown below: (21 points) 2a. The critical path is and its length is weeks. 2 26. The

2. Answer Questions 2a 2c using the figure shown

2. Answer Questions 2a 2c using the figure shown below: (21 points) 2a. The critical path is and its length is weeks. 2 26. The total slack time in Activity "D" is weeks 3 2c. If the crash cost/week for all activities is the same and we 6 3 1 E H can crash all activities by 2 weeks except Activity I by a week 7 and customer wants us to shorten the project length by 3 weeks, F we should crash Activity week(s) first and then crash Activity by week(s). 7 D 5 5 B 5 2 by 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image