Question: 2. Complete the table below and plot the BWSC, BCWP and ACWP as a function of time. What are your conclusions? Variances Schedule Cost EAC

2. Complete the table below and plot the BWSC,
2. Complete the table below and plot the BWSC, BCWP and ACWP as a function of time. What are your conclusions? Variances Schedule Cost EAC Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Cumulative Cost in thousands BCWS BCWP ACWP 50 50 25 70 60 40 90 80 67 120 105 90 130 120 115 140 135 130 165 150 155 200 175 190 250 220 230 270 260 270 300 295 305 350 340 340 380 360 370 420 395 400 460 460 450