Question: 7) Complete the table below and plot the EAC as a function of time. What are your conclusions? Variance $ Schedule Cost 50 25 60

7) Complete the table below and plot the EAC as a
7) Complete the table below and plot the EAC as a function of time. What are your conclusions? Variance $ Schedule Cost 50 25 60 90 120 Cumulative Cost, in Thousands Week BCWS BCWP ACWP 50 70 80 105 130 120 115 140 135 130 165 150 200 175 190 250 270 260 270 300 295 305 350 340 340 380 360 370 420 395 400 460 460 450 155 220 230