Question: 2. Consider the network described in the table below. Times are given in weeks (keep 2 decimal places). Activity Immediate Predecessor(s) Pessimistic b Most Likely
2. Consider the network described in the table below. Times are given in weeks (keep 2 decimal places).
| Activity | Immediate Predecessor(s) | Pessimistic b | Most Likely m | Optimistic a | Expected Activity Time
| Activity Variance
|
| J | -- | 15 | 10 | 8 | 10.5 | 1.36 |
| K | -- | 9 | 8 | 7 | 8 | 0.11 |
| L | J | 10 | 6 | 5 | 6.5 | 0.69 |
| M | K,L | 3 | 3 | 3 | 3 | 0 |
| N | M | 9 | 5 | 1 | 5 | 1.78 |
| O | L,N | 11 | 8 | 5 | 8 | 1 |
- Draw the network diagram.
- What is the critical path? What is the expected duration of the critical path?
- Calculate the probability that the project will be completed in more than 35 weeks.