Question: PLEASE ANSWER ALL PARTS INCLUDING A,B,C. SHOW ALL WORK PLEASE! 2. Consider the network described in the table below. Times are given in weeks (keep

PLEASE ANSWER ALL PARTS INCLUDING A,B,C. SHOW ALL WORK PLEASE!
2. Consider the network described in the table below. Times are given in weeks (keep 2 decimal places). Activity Immediate Pessimistic Most Likely Optimistic Expected Activity Activity Variance Predecessor(s) b m a Time J 15 10 8 10.5 1.36 K 9 8 7 8 0.11 10 6 5 6.5 0.69 M KL 3 3 0 N M 9 5 1 5 1.78 O L,N 11 8 5 8 1 a.- Draw the network diagram. 6.- What is the critical path? What is the expected duration of the critical path? C.-Calculate the probability that the project will be completed in more than 35 weeksStep by Step Solution