Question: 2. Consider the network described in the table below. Times are given in weeks (keep 2 decimal points). Pessimistic Most Likely Optimistic Activity Immediate Predecessor(s)

2. Consider the network described in the table
2. Consider the network described in the table below. Times are given in weeks (keep 2 decimal points). Pessimistic Most Likely Optimistic Activity Immediate Predecessor(s) b m a A 15 10 8 9 8 7 B C A,B 10 6 5 D B,C 3 3 3 E D 9 F C.E 11 8 5 a. Draw the network diagram. b. Cofculate the expected time and variance of each activity. 1 c. Calculate the probability that the project will be completed in more than 33 weeks