2-For the following project, draw the network and
a) calculate expected time for each activity: calculate the expected time for activity 8.
\table[[Node Nos.,Predecessor(s),\table[[Shortest likely],[Time]],\table[[Most likely Time],[Longest Likely],[Time]],],[1,-,1,2,3],[2,1,5,6,7],[3,1,3,4,5],[4,1,1,2,3],[5,2,2,4,6],[6,2,3,4,4,5,6],[7,2,1,3,5],[8,5,6,1,2,3]]
Answer: 2.33