Question: 2 ) In order to plan for procurements, the project team uses a project document that includes a list of deliverables, acceptance criteria, project assumptions

2) In order to plan for procurements, the project team uses a project document that includes a list of deliverables, acceptance criteria, project assumptions and constraints, and a description of the product, service or result. This document is called the _________.
a) Work Breakdown Structure (WBS)
b) Project Charter
c) Project Contract
d) Project Scope Statement