Question: 2 points In project time management, critical chain scheduling needs to include buffers to the project to add additional time that may be required to

2 points
In project time management, critical chain scheduling needs to include buffers to the project to add additional time that may be required to accommoda that may occur during the life of the project. The different types of buffer include:
Select all that apply.
task buffer
project buffer
locomotive buffer
activity buffer
feeding buffer