Question: 2. Problem (Ch. 19, Project Management) Consider the project with the following dependency matrix. Predecessor Activity 1 2 3 Activity Time (Days) 2 5 7

2. Problem (Ch. 19, Project Management) Consider

2. Problem (Ch. 19, Project Management) Consider the project with the following dependency matrix. Predecessor Activity 1 2 3 Activity Time (Days) 2 5 7 1 4 3 Oo Own 5 4 2 2 2 4,5 3,6 6,7 6 6 7 3 8 8 a) Draw an activity-on-node graph and compute the earliest completion time of the project using EST/ECT. (25 pts/100) b) Draw a Gantt chart for this project including slack times. (25 pts/100)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Lets solve this step by step Given Data Activity Predecessor Activity Time Days 1 2 2 1 5 3 2 7 4 2 ... View full answer