Question: 2. Solve the following network. Calculate ES, EF, LS, LF, TF and FF. Indicate the critical path. Solve the same network using the series method

2. Solve the following network. Calculate ES, EF,
2. Solve the following network. Calculate ES, EF, LS, LF, TF and FF. Indicate the critical path. Solve the same network using the series method for resource allocation. The resource limit is 6 H. Also, calculate the total resource requirement for each day after the resource allocation. Comment on the results. (20 points) B 3 E 5 H 3 4H 4H BH 1 2 1 1H 2H 3H D 6 G 3 6 5H 1H TH Priority is as follows: 1. Earliest Late Start Date 2. Least Total Float 3. Largest Number of Resources 4. Input Order