Question: 2. The following table indicates the activity, and time duration of each task in the development of a project: Activity Description Duration (Days) Immediate Predecessor
2. The following table indicates the activity, and time duration of each task in the development of a project:
| Activity | Description | Duration (Days) | Immediate Predecessor |
| A | Requirement Analysis | 5 | - |
| B | System Design | 15 | A |
| C | Implementation | 25 | B |
| D | Telecommunication | 15 | B |
| E | Equipment Installation | 30 | B |
| F | System Integration | 10 | C, D |
| G | System Testing | 10 | E, F |
| H | Training | 5 | G |
| I | System Deployment | 5 | H |
Draw the network for the information provided in the table (12 pts.)
Determine (specify) all paths through the network (9 pts.)
Determine the Critical Path(s) (7 pts.)
Calculate the planned duration of the project