Question: 21. Critical Path is the ______________ path in a project schedule? a. Shortest c. Most Critical b. Longest d. Riskiest 22. A project schedule must
21. Critical Path is the ______________ path in a project schedule?
| a. | Shortest |
c. |
Most Critical |
| b. | Longest | d. | Riskiest |
22. A project schedule must be baselined before ______________ can be calculated.
| a. | Project Prioritization | c. | Project Task |
| b. | Critical Path | d. | Project Managers Salary |
23. Teams conducting a risk management meetings in person are hoping to accomplish more problem solving. They are trying to establish __________?
| a. | Geographic Decentralization | c. | Symbiosis |
| b. | Synergy | d. | Group Think |
24. When a company allows too much work into the project pipeline with the same number of resources (or CT), causing WIP to increase and TP to decrease, this is an example of ______________ in action?
| a. | Phase Gate Project Management | c. | Littles Law |
| b. | Resource Contention | d. | WBS |
25. The Earned Value formula of EV / PV = _______________?
| a. | BAC | c. | CPI |
| b. | SPI | d. | ETC |
26. The worst form of project contract dispute resolution is ______________?
| a. | Arbitration | c. | Mediation |
| b. | Litigation | d. | Settlement |
27. The Earned Value formula of AC / PV = _________________?
| a. | VAC | c. | CPI |
| b. | SPI | d. | EAC |
28. Initially, risk mitigation planning on a project occurs ______________?
| a. | Ex Post Facto | c. | In WBS Planning |
| b. | After a risk trigger | d. | Once a risk is realized |
29. When reserve analysis is conducted on a project, monies are set aside to for _____________?
| a. | Portfolio Management | c. | Management Reserve |
| b. | Program Management | d. | Enterprise Management |
30. Contingency Reserve monies are set aside to fund _______________?
| a. | Previous Plans | c. | Contingencies |
| b. | Tactical Plan | d. | Strategic Plan |