Question: 2.1 Given the following data: Predecessor Activity a b d a b b e f Duration (days) 10 15 17 5 4 15 7 8

2.1 Given the following data: Predecessor
2.1 Given the following data: Predecessor Activity a b d a b b e f Duration (days) 10 15 17 5 4 15 7 8 12 10 g h i j d e f ghi Draw the network and calculate and calculate the Critical Path. 2.2 South Africa celebrates Women's Day on the 9th August. The local government has contracted you to plan the 2020 celebration. Client specifications are as follows: Estimated no. of 5000 delegates Must include a lunch meal Must include 1 soft-drink per delegate Must include a Program for the day Budgeted Amount R 1 650 000 Prepare a: 2.2.1 Gantt Chart (a minimum of 10 activities) 2.2.2 Construct a Work Breakdown Structure (graphical format) (6) (9)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!