2:19PM e e 7.5 Practice quiz: The pr... uct.onlinecampus.getsmarter.com 1 Question Not yet answered Marked out of 1.00 The project manager holds weekly, scheduled status meetings with the team. The meetings have been disorganised, chaotic, and lacking direction. Which one of the following actions would immediately improve the meetings to make them more effective? Select one: b. O Publish an agenda during the meeting. Determine who is involved in the meeting. Send the team to communication training. Publish an agenda ahead of the meeting, and follow it during the meeting. Question 2 40t yet answered Marked out of 1.00 Chat to us!