Question: 22. There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed

22.

There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by 110 days. The maximum possible reduction in the project duration will be:

a.0 days

b.110 days

c.660 days

d.220 days

e.Insufficient information

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!