Question: There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by
There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by 61 days. The maximum possible reduction in the project duration will be:
a. Insufficient information
b. 0 days
c. 366 days
d. 61 days
e. 122 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
