Question: here are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by

here are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by 25 days. The maximum possible reduction in the project duration will be:

a. 0 days

b. 150 days

c. 25 days

d. 50 days

e. Insufficient information