Question: 23,24,25 PROBLEM B The following table contains information about a project. Use it to answer the problems 23 - 25: Activity Normal Time Normal Cost

23,24,25 23,24,25 PROBLEM B The following table contains
PROBLEM B The following table contains information about a project. Use it to answer the problems 23 - 25: Activity Normal Time Normal Cost Crash Time Immediate Predecessors Crash Cost SO 6,000 zo S WONOWA d. BEG 23. What is the critical path? a. ADFG b. BDFG C.ACFG 24. What is the expected project completion time? b. 26 c. 18 a. 19 d. 17 c. 28 25. How much will it cost to reduce the completion time of the project by 3 weeks (at least direct cost)? a. $3,500 b. $2,500 c. $6,000 . 56,500 search OH Nw