Question: 39,40 PROBLEM G The following table contains information about a project. Use it to answer the problems 39 - 40: The Project Manager is about
39,40
PROBLEM G The following table contains information about a project. Use it to answer the problems 39 - 40: The Project Manager is about to begin a project comprised of the following six activities: TIME ESTIMATES (days) Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic 15 9 10 K- L M NK.M N K.M P LN 39. What is the expected (mean) time for project completion? A) 23 days B) 66 days C) 26 days D) 31 days E) 47 days 40. What is the probability that the completion time for this project will be greater than 28 days? A) 0.8264 B) 0.7544 C) 0.6772 D) 0.4987 E) 0.1736