Question: 39,40 PROBLEM G The following table contains information about a project. Use it to answer the problems 39 - 40: The Project Manager is about

39,40
39,40 PROBLEM G The following table contains
PROBLEM G The following table contains information about a project. Use it to answer the problems 39 - 40: The Project Manager is about to begin a project comprised of the following six activities: TIME ESTIMATES (days) Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic 15 9 10 K- L M NK.M N K.M P LN 39. What is the expected (mean) time for project completion? A) 23 days B) 66 days C) 26 days D) 31 days E) 47 days 40. What is the probability that the completion time for this project will be greater than 28 days? A) 0.8264 B) 0.7544 C) 0.6772 D) 0.4987 E) 0.1736

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!