Question: Consider the following project network, with task duration data provided: Which of the following is the completion time for this project? a. 8 days b.

 Consider the following project network, with task duration data provided: Which
of the following is the completion time for this project? a. 8

Consider the following project network, with task duration data provided: Which of the following is the completion time for this project? a. 8 days b. 11 days Which of the following is the completion time for this project? a. 8 days b. 11 days c. 9 days d. 12 days e. 10 days