Question: 4 Moving to another question will save this response. Question 23 Question 23 1.923 points What should be the estimate to construct a new warehouse
4 Moving to another question will save this response. Question 23 Question 23 1.923 points What should be the estimate to construct a new warehouse with 3600 m2, if a similar recently completed warehouse with 2900 m2 costs $623.500 $ 774,000 $ 900,000 $ 700,000 $ 835,000 Close Window A Moving to another question will save this response Question 24 of 52 Question 24 it for a particular project acthin the pressimis 19 entrate : 3000 AD, the Optimiste 101 estimates 2000 AED while Most Likely Mestimate s 4200 AED), the BETA three point 1.923 points La estimate will equal to: AED 5433 AED 4533 AED 4833 AED 4133 Question 25 1.923 points During the nation of the project, you found that the total planned costs of your project were 5400,000. The actual costs were $230,000. How can you describe the project performance There is no mugh information The project is exceeding is budget The project is head of Schedule The projects within budget Question 25 of 2 Mowing the question with response Clone Window to 262 Question 26 You are working for a contraction company. As you view the project results, you notice you have spent 1.200,000 the last reporting point. The schedule performance index I os. Considering you need to spend 2400,000 to this point. What is the cost performance Index? 05 2 4 Moving to another question will save this response. Question 23 Question 23 1.923 points What should be the estimate to construct a new warehouse with 3600 m2, if a similar recently completed warehouse with 2900 m2 costs $623.500 $ 774,000 $ 900,000 $ 700,000 $ 835,000 Close Window A Moving to another question will save this response Question 24 of 52 Question 24 it for a particular project acthin the pressimis 19 entrate : 3000 AD, the Optimiste 101 estimates 2000 AED while Most Likely Mestimate s 4200 AED), the BETA three point 1.923 points La estimate will equal to: AED 5433 AED 4533 AED 4833 AED 4133 Question 25 1.923 points During the nation of the project, you found that the total planned costs of your project were 5400,000. The actual costs were $230,000. How can you describe the project performance There is no mugh information The project is exceeding is budget The project is head of Schedule The projects within budget Question 25 of 2 Mowing the question with response Clone Window to 262 Question 26 You are working for a contraction company. As you view the project results, you notice you have spent 1.200,000 the last reporting point. The schedule performance index I os. Considering you need to spend 2400,000 to this point. What is the cost performance Index? 05 2