Question: please solve !! Moving to another question will save this response Question 2 ICH 7) A project was estimated to cost AED 1.5M and scheduled




Moving to another question will save this response Question 2 ICH 7) A project was estimated to cost AED 1.5M and scheduled to last for 6 months. After three months, what would be the Schedule Variance given the following earned value analysis in AED? EV - AED 650,000, PV = AED 750,000 AC - AED 300,000 O-100,000 b. 100.000 oc 50.000 d.+50,000 Moving to another question will save this response. Moving to another question will save this response. Question 8 For a given project with AED 225,000 budget, 25 percent was completed. What would be the earned valued? a. 56,250 b. 168,750 c. 900,000 d, 450,000 & Moving to another question will save this response. Timed Test This best has a me Warnings appear when half the time 5 minutes, 1 minute, and 30 seconds remain Multiple Attempts Not allowed. This test can only be taken once Force Completion This test can be saved and resumed at any point until time has expired. The time will continue to run if you leave the test. Remaining Time: 44 minutes, 5 seconds Question Completion Status: Moving to another question will save this response. Question 23 ICH 11) If a business venture has a 60-percent chance to earn AED 2 million and a 20-percent change to lose AED 15 million, what is the expected monetary value of the venture in AED? -- 50.000 - 300,000 -500,000 d. 900,000 Moving to another question will save this response. 19 Question 24 (CH 11) Consider the figure below and assume that the risk has a 75 percent probability of occurrence. negative impact equivalent to AED 200,000 or AED 50,000, respectively, with the given probabilities. Wha Possible Impacts Opportunity worth $200.000 Probabw40 Risk Probability60% Threat of losind $50.000 O a. 80,000 b. 200,000 C. 40,000 d. 60,000 16 17 19 20 21 25 3 points figure below and assume that the risk has a 75 percent probability of occurrence. If the risk does occur, it could have a positive or a Jvalent to AED 200,000 or AED 50,000, respectively, with the given probabilities. What is the EMV for the positive impact in AED? Possible impacts Opportunity worth $200,000 -40% Threat of losing $50,000 e this response
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
