Question: 3 . 7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: table [ [ Activity

3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows:
\table[[Activity,Time (in hours),\table[[Immediate],[Predecessors]]],[A,6.0,-],[B,7.2,-],[C,5.0,A],[D,6.0,B, C],[E,4.5,B, C],[F,7.7,D],[G,4.0,E, F]]
a) Draw the project network using AON.
b) Identify the critical path.
c) What is the expected project length?
d) Draw a Gantt chart for the project.