Question: Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: table [ [ Activity , Time (

Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows:
\table[[Activity,Time (in hours),\table[[Immediate],[Predecessors]]],[A,6.0,-],[B,7.2,-],[C,5.0,A],[D,6.0,B, C],[E,4.5,B, C],[P,7.7,D],[G,4.0,E. F]]
Draw the project network waing AON.
b) Identify the criticel path.
c) What is the expecied yroject leagth?
d) Draw a Gasis chari for the project