Question: 3.7 Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Time (in hours) Immediate Predecessor(s) A
3.7 Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows:
|
Activity | Time (in hours) | Immediate Predecessor(s) |
| A | 6.0 | --- |
| B | 7.2 | ---- |
| C | 5.0 | A |
| D | 6.0 | B,C |
| E | 4.5 | B,C |
| F | 7.7 | D |
| G | 4.0
| E,F |
|
|
- Draw the project network using AON.
- Identify the critical path
- What is the expected project length?