Question: Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Activity Time (in hours) Predecessors A 6.0

Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Activity Time (in hours) Predecessors A 6.0 CRCDEFG B 7.2 5.0 A 6.0 B, C 4.5 B, C 7.7 D 4.0 E, F

a) Draw the project network using AON.

b) Identify the critical path.

c) What is the expected project length?

d) Draw a Gantt chart for the project. P