Question: 3 . A CPM network diagram is drawn using AOA ( activity on arrow ) format to analyze the schedule. The dotted arrow line is

3. A CPM network diagram is drawn using AOA (activity on arrow) format to analyze the schedule. The dotted arrow line is a dummy (no activity, only shows precedence).
Immediate
Activity Pred. Duration (day)
a -3
b a 4
c a 5
d -3
e d 6
f b,c,e 7