Question: A network diagram is drawn using AOA ( activity on arrow ) format to analyze the schedule: Calculate ES , EF , LS , LF

A network diagram is drawn using AOA (activity on arrow) format to analyze the schedule:
Calculate ES, EF, LS, LF and Slack for all activitics.
a) How long is the project duration?
b) If all activities are on schedule and then activity "b" is delayed by 2 days, what is your new estimate on total project duration?
c) If all activities are on schedule and then activity "e" is delayed by 2 days, what is your new estimate on total project duration?
 A network diagram is drawn using AOA (activity on arrow) format