Question: A CPM network diagram is drawn using AOA (activity on arrow) format to analyze the schedule: Immediate Activity Pred. Duration (day) a - 3 b
- A CPM network diagram is drawn using AOA (activity on arrow) format to analyze the schedule:
Immediate
Activity Pred. Duration (day)
a - 3
b a 4
c a 5
d - 3
e d 6
f b,c,e 7
a) Show all potential paths and their durations.
b) Calculate ES, EF, LS, LF and Slack for all activities.
c) How long is the project duration?
d) If activity a is delayed by 2 days, what is your new estimate on total project duration?
e) If all activities are on schedule and then activity e is delayed by one day, what is your new estimate on total project duration?