Question: 3. Activity Immediate Predecessor Normal Time (Days) Normal Cost ($) Crash Time (Days) Crash Cost ($) A ------- 8 5,000 6 6,000 B A 8
3.
Activity | Immediate Predecessor | Normal Time (Days) | Normal Cost ($) | Crash Time (Days) | Crash Cost ($) |
A | ------- | 8 | 5,000 | 6 | 6,000 |
B | A | 8 | 4,000 | 8 | 4,000 |
C | B | 12 | 6,000 | 10 | 10,000 |
D | B | 6 | 3,000 | 6 | 3,000 |
(a) Draw the Precedence Diagram for the above project, complete with ES, EF, LS, and LF.
(b) What is the Critical Path?
(c) What is the Project Completion Time under normal schedule?
(d) If the total project time has to be crashed by TWO days, which activity will you choose?