Question: 3. Activity Immediate Predecessor Normal Time (Days) Normal Cost ($) Crash Time (Days) Crash Cost ($) A ------- 8 5,000 6 6,000 B A 8

3.

Activity

Immediate

Predecessor

Normal

Time (Days)

Normal

Cost ($)

Crash

Time (Days)

Crash

Cost ($)

A

-------

8

5,000

6

6,000

B

A

8

4,000

8

4,000

C

B

12

6,000

10

10,000

D

B

6

3,000

6

3,000

(a) Draw the Precedence Diagram for the above project, complete with ES, EF, LS, and LF.

(b) What is the Critical Path?

(c) What is the Project Completion Time under normal schedule?

(d) If the total project time has to be crashed by TWO days, which activity will you choose?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!