Question: 3 Exercise 2 a. Draw the Network Diagram. Use two-pass method to calculate and show the early and late: slack for each activity. Highlight the

3 Exercise 2 a. Draw the Network Diagram. Use
3 Exercise 2 a. Draw the Network Diagram. Use two-pass method to calculate and show the early and late: slack for each activity. Highlight the Critical Path. b. Using the Enumeration Method list all the network paths with length. Activity Details Duration (days) Predecessor(s) A Dig Holes Buy Wood 2 Dig Holes C Buy Gate Dig Holes D Erect Fence 3 Buy Wood E Buy Paint Buy Gate F Erect Gate Erect Fence, Buy Paint G Paint Fence 2 Erect Gate Paint Gate 1 Paint Fence 1