Question: Exercise 1 Draw the Network Diagram. Use two - pass method to calculate and show the early and late starts and slack for each activity.

Exercise 1
Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Using the Enumeration Method list all the network paths with length. (i.e. A-B-C-D=12) What is the Critical Path? How do you know it is the CP?
Activity Details Duration (days) Predecessor(s) A Dig Holes 3- B Buy Wood 2 Dig Holes C Buy Gate 1 Dig Holes D Erect Fence 3 Buy Wood E Buy Paint 1 Buy Gate F Erect Gate 1 Erect Fence, Buy Paint G Paint Fence 2 Erect Gate H Paint Gate 1 Paint Fence
 Exercise 1 Draw the Network Diagram. Use two-pass method to calculate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!