Question: Exercise 4 Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the
Exercise 4
- Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the Critical Path.
- Using the Enumeration Method list all the network paths with length.
| Activity | Duration (days) | Predecessor(s) |
| A | 2 | - |
| B | 3 | - |
| C | 4 | A,B |
| D | 5 | C |
| E | 2 | D |
| F | 3 | D |
| G | 4 | E |
| H | 2 | F |
| I | 2 | G,H |