Question: 3. Find the completion time for this construction project, and calculate slack times for activities in path 1-2-4-6-7. (25 points) 3 Lay foundation Dummy 1

3. Find the completion time for this construction
3. Find the completion time for this construction project, and calculate slack times for activities in path 1-2-4-6-7. (25 points) 3 Lay foundation Dummy 1 2 1 Order materials Build house 3 3 2 Design house and obtain financing Finish work 1 6 7 1 Select paint Select carpet 5