Question: 3. Find the completion time for this construction project, and calculate slack times for activities in path 1-2-4-6-7. (25 points) Lay foundation Dummy 2 3

3. Find the completion time for this construction
3. Find the completion time for this construction project, and calculate slack times for activities in path 1-2-4-6-7. (25 points) Lay foundation Dummy 2 3 Build house 3 Finish work 1 1 Design house and obtain financing Order materials Select paint Select carpet

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock